Joe,
Special Procurement key for Plant B should be Look Like This see below
Special procurement key can be any number you define as in your case its 70
Procurement type should be F and Special Procurement data should be U and the Source Plant.
Then In material Master the MRP 2 should have the special key as you defined.
I hope once you do this this should be ok.
Thanks
Hrusikesh